    GHMC bent on full SNDP functions throughout city

    Related stories

    Hyderabad Fuel Vendors in Need of Assistance for Uncertain Future

    Retail petroleum dealers in Hyderabad are considering going on...

    Bombshell dropped by PFC in Hyderabad

    The Kaleshwaram mega project in Hyderabad, known as the...

    Telkapally SI Naresh seizes illegally transporting sand tractor

    A sand tractor was seized by Sub inspector Naresh...

    Greater Hyderabad Municipal Corporation

    - Advertisement -

    Greater Hyderabad Municipal Corporation

    Hyderabad: To guarantee that no flooding like scenario happens in the city throughout the downpour, the Greater Hyderabad Municipal Corporation (GHMC) design wing authorities on Thursday were asked to finish all the development functions used up under the Strategic Nala Development Plan (SNDP) in the city

    - Advertisement -

    SNDP used up worth ‘958 cr under Phase- I.

    ♦ Development of 60 nalas

    - Advertisement -

    ♦ Of the complete 60 jobs, 37 fall under GHMC, continuing to be come from bordering communities.

    ♦ Of the 37 jobs,13 of them are full, 6 even more to be ended up by March- end

    8 even more jobs to yet to finish.

    ♦ Four to be ended up by February- end.

    ♦ Rest 4 by March- end

    SNDP functions consist of

    ♦ Building bridges/culverts

    ♦ Repairing existing drains pipes

    ♦ Widening stormwater (SW) drains pipes

    ♦ Constructing preserving wall surfaces near little SW drains pipes

    ♦ Building box drains pipes

    Works used up in all 6 areas 

    ♦ 8 in Secunderabad

    ♦ 3 in Kukatpally

    ♦ 10 in POUND Nagar area

    ♦ 7 in Charminar, Khairatabad each

    ♦ 2 in Serilingampally

    Works finished till day

    ♦ Construction as well as overhaul of SW drains pipes in between numerous lakes consisting of Nagireddy Cheruvu-Kapra Lake, Modugula Kunta-Kotha Cheruvu, Mansurabad Cheruvu-Bandlaguda Lake, Bandlaguda Lake-Nagole Lake, Bathula Cheruvu-Injapur Nala, as well as Appa Cheruvu-Mulgund Lake stretches.

    ♦ Bridges on SW drains pipes at VST, Nallakunta as well as SP Road in Secunderabad

    ♦ Construction of a web link in between 2 drains pipes in Patancheru

    ♦ Construction of culvert in Karwan

    ♦ Two drains pipes in Chandrayangutta as well as Bandlaguda, 1 in Chandanagar

    ♦ The long-pending work with the Balkapur nala in Karwan would certainly be finished by summertime end.

    Works under SNDP Phase- II

    ♦ To cover 415 nala functions covering 450 kilometres in GHMC as well as adjoining ULB.

    ♦ Of this, 148 nalas of complete size of 175 kilometres remain in GHMC restrictions.

    ♦ Remaining 267 nalas covering a range of 275 kilometres remain in ULBs bordering the city

    Also read:  BRS might adjust strategy for LS election campaign
    - Advertisement -
    Rajesh M
    Rajesh Mhttps://www.telanganatribune.com
    Latest News from Hyderabad, Telangana, India & World!

    Follow us

    3,565FansLike
    179FollowersFollow
    1,202FollowersFollow
    965SubscribersSubscribe

    Contribute News

    You can contribute an article to Telangana Tribune by dropping a mail at newsdesk@telanganatribune.com

    Latest stories

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here