HYDRAA is carrying out a restoration project worth about ₹35 crore at Kapra Lake in Hyderabad. The lake is one of 14 waterbodies included in the second phase of the agency’s lake restoration programme.
Nearly 60% of the work has been completed, according to HYDRAA. The project covers the lake’s 112.80-acre full tank level (FTL) area, and local residents have been visiting the site to see the progress.
Farmers who own land within the lake boundaries have voluntarily offered 70 acres in the FTL area for development. HYDRAA said the farmers met its commissioner and submitted a letter of consent.
HYDRAA says Kapra Lake supports migratory birds and local biodiversity. The agency has said the Centre recognises the lake as a wetland important to the city’s ecological balance, and that it provides a habitat for more than 470 migratory bird species.
The restoration includes desilting to increase the lake’s water-holding capacity and help filter pollutants and waste naturally. HYDRAA is also increasing the lake’s depth to store more rainwater and support groundwater recharge.
Work is under way to improve the lake’s inlet and outlet systems and build a walking track around the waterbody. A strong fence is also being installed to protect the lake’s boundaries and prevent future encroachments.
The project is intended to support flood control during heavy rain and protect habitats for fish, birds, amphibians and other aquatic life. HYDRAA’s plans include public access for walkers and local residents while retaining the lake’s ecological functions.