Hyderabad Metro is redesigning the MGBS–Chandrayangutta corridor after securing land through agreements with property owners in congested areas. The changes aim to lower construction costs while keeping the route within the busy urban stretch.
The revised design will align the tracks along the road’s centreline and reduce the number of expensive portal pillars. More than 30 portal pillars were originally planned for the corridor, which spans 7.5 km and has an estimated cost of ₹2,935 crore.
The corridor will have six stations, spaced about 1.2 km apart: Salarjung Museum, Charminar, Shalibanda, Aliabad, Falaknuma and Chandrayangutta. Alternative structural designs are planned near historical buildings to protect heritage structures.
Separately, the deadline for the General Consultancy (GC) tender covering four metro corridors has been extended from September 24 to October 8.