In Hyderabad, a senior irrigation official revealed that the previous BRS government added six extra vents to the second Block A of the Sundilla barrage without including them in the Detailed Project Report (DPR).

Fazal, a superintendent engineer from the Central Design Organisation (CDO), testified before the Justice Ghose Commission on the Kaleshwaram project on Friday. He stated that the cross sections of the dams were approved based on reports from the Kaleshwaram Chief Engineer (CE) without any site inspections.

The Kaleshwaram CE had recommended the use of secant piles in the construction of the Medigadda Dam, following advice from the National Institute of Technology (NIT) Warangal.

Advertisement

The six additional vents in the second Block A of Sundilla were not part of the original design plans. Their construction was carried out based on a decision made by the cabinet.

Also read:  Arrest Made After GHMC Anti-Encroachment Drive Obstructed at Murgi Chowk in Hyderabad

On the second day of the hearing, retired CDO Engineer-in-Chief Narender Reddy also appeared before the Commission. He submitted two letters related to the ongoing investigation into the Kaleshwaram project.

Advertisement
Disclaimer: For article corrections, please email newsdesk@telanganatribune.com or fill out the Grievance Resolution form
Who will be the next CM of Telangana?
KCR / KTR / Harish Rao
Revanth Reddy
Others
Download our App:
About the Author
Rajesh M
Rajesh M

Latest News from Hyderabad, Telangana, India & World!

Leave a Reply

Your email address will not be published. Required fields are marked *