Vattem Pump Motors Tested Successfully

Vattem Pump Motors Tested Successfully
Text Size: 100%

Dry Run of Vattem Pump Motors Successfully Completed

The Vattem pump motors at the Vattem Venkataadri Reservoir in Nagarkurnool district have successfully completed a dry run. This reservoir is a key part of the Palamuru-Rangareddy Project. The trial took place on Thursday and was overseen by Penta Reddy, the Government Advisor for Irrigation, along with engineers CE G. Vijay Bhaskar Reddy, SE Satyanarayana, and EE Parthasarathy. During the process, the first pump motor was successfully made operational.

Two months ago, the pump house faced severe challenges due to heavy rains. Floodwater from the Sri Puram area auditor tunnel entered the Vattem pump house, submerging the motors. To address this issue, the state government initiated special efforts to drain the water and repair the motors, restoring them to working condition.

Also read:  Telangana Cabinet Clears Major Decisions on E-Autos, Ration Cards, Irrigation and Jobs

Now that the first motor is fully operational, work is in progress to make the remaining motors functional as soon as possible. This marks a significant step in restoring the pump house to full capacity.

Advertisement
Disclaimer: For article corrections, please email [email protected] or fill out the Grievance Resolution form
KCR / KTR / Harish Rao
Revanth Reddy
Others
About the Author
Newsdesk
Newsdesk

Latest News from Hyderabad, Telangana, India & World!

Leave a Reply

Your email address will not be published. Required fields are marked *